Project Schedule:

  • Preliminary Engineering report developed – May 2008 Complete
  • Design initiated - March 2009  Complete
  • Mobilization activities – May 2009  Complete
  • Anticipated MDC Approval – June 2009  Complete
  • Construction begins - June/July 2009  In Progress
  • Project completion - Summer/Fall 2010

A simple project fact sheet with basic information is available. A recent presentation to a group of interested neighbors provides more detail.  

Draft Landscaping Plan (updated 21 May 09)

February 2, 2010 UPDATE

There will be a considerable amount of concrete work ocurring at the plant during the next two weeks.

Next 2 weeks

  • Pour slabs and walls at the Actiflo Building.
  • Remove shoring from the UV Building.
  • Install pipe and new clarifier equipment at the low basin at the Gravity Thickener.
  • Install new baffles in the existing chlorine contact tank.
  • Install tube settler support steel in the high basin.
  • Install low basin clarifier (zone2).

 