Upgrades at T.W. Moses Facility
Work to continue through summer/fall 2010
To ensure compliance with more stringent drinking water standards, Veolia & Indianapolis Water are making substantial improvements to the T.W. Moses Water Treatment Facility near Eagle Creek Park.
When complete, the improvements will improve drinking water quality and provide additional protection from disease-causing microorganisms and contaminants that can form during drinking water treatment processes.
Project Schedule:
- Preliminary Engineering report developed – May 2008 Complete
- Design initiated - March 2009 Complete
- Mobilization activities – May 2009 Complete
- Anticipated MDC Approval – June 2009 Complete
- • Construction begins - June/July 2009 In Progress
- Project completion - Summer/Fall 2010
A simple project fact sheet with basic information is available. A recent presentation to a group of interested neighbors provides more detail.
Draft Landscaping Plan (updated 21 May 09)
November 20, 2009 UPDATE
There will be a considerable amount of concrete work ocurring at the plant during the next two weeks.
Next 2 weeks
Pour concrete columns and install shoring at Actiflo Building
Pour concrete baffle walls at UV Building
Backfill, install pipe and equipment at the Gravity Thickener
Continue Masonry at Plate Settler Building
![]() |
|
Above left: The UV Building starts to take shape.
Above right: The Gravity Thickener is leak-tested.