Upgrades at T.W. Moses Facility

Work to continue through summer/fall 2010

To ensure compliance with more stringent drinking water standards, Veolia & Indianapolis Water are making substantial improvements to the T.W. Moses Water Treatment Facility near Eagle Creek Park.

When complete, the improvements will improve drinking water quality and provide additional protection from disease-causing microorganisms that may be present in raw water, and from contaminants that can form during drinking water treatment processes.

Project Schedule:

  • Preliminary Engineering report developed – May 2008 Complete
  • Design initiated - March 2009  Complete
  • Mobilization activities – May 2009  Complete
  • Anticipated MDC Approval – June 2009  Complete
  • Construction begins - June/July 2009  In Progress
  • Project completion - Summer/Fall 2010

A simple project fact sheet with basic information is available. A recent presentation to a group of interested neighbors provides more detail.  

Draft Landscaping Plan (updated 21 May 09)

June 18, 2010 UPDATE

The T.W. Moses Treatment Plant was returned to service in April. It had been out of service during since December. The portions of the technical upgrades project that have been put into service include; new sludge collectors and tube settlers in both basins, the re-baffled contact basin, and new filter effluent piping.

Construction will continue through the summer and in to the fall of 2010.

Work to be completed during the next two weeks:

  • plate settler pipe
    plate settler Polymer – pour equipment pads, set skids, set scale, overhead door set
    dewater existing clarifier into other clarifier
    PAC mixer area
    pours beams
    mixer pads and boxes
    strip shoring
    strip pads in Plate Settler Bldg
    door frames in Chemical Bldg
    doors and openings in UV Bldg
    chemical bldg layout dowels – interior walls – block inside
    chemical bldg masonry
    paint UV electrical room – Bldg
    roofing - UV

 twm_UV1.png twm_Tank.png 

 platesettlerinstallation.png uvbuildingmasonry.png 

Above left: The UV Building starts to take shape.

Above right: The Gravity Thickener is leak-tested.